Before taking possession of the flats purchased by any individual, obtaining
Occupation Certificate (OC) is a “must have document”. If you are denied of the
same, then the consumer court can come to your rescue.
The
Bandra Consumer Disputes Redressal Forum noting that the Occupancy Certificate
is an essential requirement for a flat-buyer, has ordered Dharia Developers to
give the purchaser, the Occupancy Certificate within a specified time.
As
per an agreement dated September 26, 2006,
Mr. Mehul Thakkar bought two flats on the sixth floor (601 and 602) of
an apartment building by paying Rs 40.25 lakh for each of the flats, the
remaining one lakh per flat was agreed to be paid at the time of delivery
of possession. It appears that M/s.
Dharia Developers had promised to give the possession of the flats within 12
months from the date of agreement. However, Thakkar is yet to obtain the
Occupancy Certificate or the Completion Certificate for these flats. Hence, Thakkar sent a notice to the builder
demanding the same. When the builder didn't respond, Thakkar filed a complaint
before the Forum and also an application seeking interim relief.
In
their defence, Dharia Developers argued that Thakkar wanted to merge both theflats into a single unit, as per his letter in September 2006. The builder
claimed that though this was against the building's approved plan, they
permitted Thakkar to do so at his own expense after getting an approval from
the sanctioning authorities. The builder stated that since Thakkar couldn't
complete the work in time, the Occupancy Certificate couldn't be obtained from
the authorities. Hence, they are not responsible for the delay in handing over
the possession and the Occupancy Certificate to Thakkar.
In
their interim order, which is common for both of Thakkar's flats, the BandraConsumer Disputes Redressal Forum has held the builder as having committed
deficiency of service. The forum observed, “These explanations are hardly
satisfactory, because it was an obligation incurred by Thakkar. If Thakkar had
not carried out the modifications that he had suggested, the builder could have
completed the construction disregarding Thakkar's suggestions.” The forum noted
that though Thakkar had given the letter informing of the modifications to the
builder in September 2006, the flat's construction is incomplete even after
three years. “The builder should have completed the constructions, internal as
well as external, as per the original plan, since the modifications were at
Thakkar's instance. The builder was not required to wait till the modifications
were completed. This shows that the builder has put forward a lame excuse for
not completing the construction and for not obtaining the Occupancy
Certificate. The builder received almost the entire consideration of the flat,
more than Rs 40 lakh in 2006. He has retained the amount and utilized the same,
but has not collected the Occupancy Certificate.”
The Forum also held, “Obtaining OC is an essential requirement under the MOFA (Maharashtra Ownership Flat Act) and the flat purchased cannot be legally occupied, unless the Occupancy Certificate is obtained by the builder. The builder has not produced a single piece of paper to show that he has taken effective steps with the competent authority for obtaining Occupancy Certificate.”
The Forum also held, “Obtaining OC is an essential requirement under the MOFA (Maharashtra Ownership Flat Act) and the flat purchased cannot be legally occupied, unless the Occupancy Certificate is obtained by the builder. The builder has not produced a single piece of paper to show that he has taken effective steps with the competent authority for obtaining Occupancy Certificate.”
No comments:
Post a Comment