In concrete construction, the importance of curing cannot be over-emphasized. Concrete
which is not adequately cured and loaded before it attains full strength is
very likely to develop cracks. The cracks in concrete adversely affect its durability by corrosion of reinforcement.
IS 456-2000 (plain
and reinforced concrete – code of practice) defines curing as “the process of
preventing the loss of moisture from the concrete while maintaining a satisfactory temperature regime”. The moisture loss takes place in two
ways. One is by evaporation caused by
the heat generated during hydration of cement. Second is by evaporation aided
by atmospheric temperature and wind. The evaporation caused by wind and
atmospheric temperature increases when the exposed surface area of concrete
increases.
In the case of
horizontal surface such as top of flat
slabs, moisture loss is prevented by ponding – making a pond 8 cm to 10 cm deep
and keeping it filled with water. If the surface is sloped or vertical, ponding
is not possible. Such surfaces are
covered by a layer of sacking, canvas, hessian or similar materials and kept constantly wet. IS 456-2000 stipulates that exposed surfaces shall be kept
constantly wet at least for seven days if ordinary Portland cement is used, and
at least for 10 days, where mineral admixtures or blended cement are used.
IS 456-2000 permits
removal of vertical form-work of column, beams and walls after a lapse of 24
hours of placing concrete. It also permits removal of form work from the
underside of slabs after three days if propos (vertical supports) are re-fixed
immediately. Removal of formwork from
the underside of slabs exposes the entire surface to atmosphere and abets
moisture loss. This part cannot be kept
wet by ponding or by covering with sacking or hessian. Spraying of water is also not effective to
keep the surface constantly wet. Thus, removal of formwork conforming to
provisions of is code makes it virtually impossible to comply with the provision
regarding continuous curing of exposed surfaces for seven or 10 days.
To speed up
construction, the columns above the slab are raised the very next day of
casting the slab. When column raising
and shuttering for the upper slab are in progress, the ponding of the top
surface of the slab is often neglected as it inconveniences the workers engaged
in form work erection. The ultimate result is inadequate curing adversely affecting the strength and durability of concrete.
Now-a-days, there
is a craze for shorter cycle time for slab casting. The cycle time is the interval between
casting one slab and the slab immediately above it. A 10-day cycle time means
once the slab at a particular level is cast, the slab immediately above it will
be cast within 10 days. The concrete attains design strength in 28 days. Within that period, two upper slabs will be
cast if the cycle time is 10 days. Form work blow the lower slab will have been removed, because IS code
permits removal of vertical support below the slab (spanning upto 4.5 metre)
after a lapse of seven days. The
stipulation that forms shall not be released until the concrete has achieved a
strength of at least twice the stress to which concrete may be subjected to at
the time of removal of form work is conveniently overlooked. Thus, a 10-day-old slab, which, in all
probability is not properly cured, carries the weight of the slab immediately
above it. It is also subjected to impact load caused by the vibration of concrete and movement of trolleys carrying concrete.
Another instance of
speed affecting quality of construction is in masonry and plastering. Bricks
required for brickwork in cement mortar should be soaked in water at least for
six hours. Earlier, the practice was to keep the bricks overnight in a tank
filled with water and take them out in the next day for use in masonry. This practice is now seldom followed. The
present day practice is to spray water on bricks kept in stacks. By this, the bricks in the inner layers
sometimes even do not get wet. Brick, if not properly soaked in water, absorbs
water from the mortar in the joints and it reduces the bonding between bricks
and results in masonry with poor strength. Brick, if not properly soaked, will absorb water from the plaster mortar also. This will result in development of cracks in the plaster, which might also break up. The brickwork in cement
mortar should be cured for seven days and plastering should be done only after
the curing. But, to save time, it is a
common practice to start plastering earlier. This too results in development of
cracks in plaster. Concrete blocks are being widely used in place of
brick. These blocks should be cured for
28 days for attaining full strength. It is now a common practice to use it much
earlier.
Owners should
resist the temptation to set unrealistic deadlines. Contractors in their eagerness to get the order should resist the temptation to accept such deadlines. Time is money, no doubt. But
trying to save money by sacrificing quality will prove only counter-productive.
No comments:
Post a Comment